September 1, 2023 12:20 PM

Roadway Closure Alert - September Begins Stages 9-12

o Work on Harper will include phases 9-12 (see attached map). Beginning on the south side of the street, underground crews will work towards Auden from Edloe, followed by the street pavement crew. The work will proceed as a moving 600 feet road closure and the contractor will reconstruct 100 feet at a time. As the 600 feet closure moves west, the roadway will be opened in 100 feet sections behind it. When the South side of Harper is complete, the contractors return to Edloe and complete the north side of Harper, working towards Auden. Street parking will be limited, and vehicles are encouraged to park on neighboring streets. Edloe and Auden may be used for parking when you do not have access to your driveway. All driveways will be accessible over Thanksgiving, Christmas, and New Years holidays. Work on Harper is expected to be complete in January.